Hydro
Demolition
A Process
was needed to reduce the time need to rehabilitate a bridge
deck for a project in Bertie County. The project would take
18 months using standard methods forcing traffic to be detoured
for 50 miles during the rehabilitation of the structure.
A project in Columbia, SC was using the Hydro-Demolition
process for dual three lane structures on I-77. Each structure
was approximately 5500 feet long. The Bertie County structure
is approximately 1 mile long. Both structures in SC were
completed and open to traffic in 25 days. The Bridge Maintenance
Unit set up a pilot project using the Hydro-Demolition in
Greene County. The Greene County project, using our standard
method of deck rehabilitation would have taken 14 weeks.
Using Hydro-Demolition, the project was complete and open
to traffic within 2 weeks. Using this project on the Bertie
County project will reduce the time from 18 months to 30
days.
Results
For the Greene County project time was reduced from 14 weeks
to 2 weeks saving 85.7% of required time. In addition the project,
using the new process, saved $230,205.42.
|
|